The remedial works on the invert located on the Slovenian side of the Karavanke tunnel

Thursday, September 4, 2014 1:30:00 PM

Schedule of planned closures of the Karavanke tunnel starting on 15 September 2014, the contractors will carry out the last phase of the remedial works on the invert located on the Slovene side of the Karavanke Tunnel on the A2 Motorway. At the same time, they will start making upgrades to the ventilation system throughout the tunnel.

The work will require the partial and complete closures of the tunnel:
• 15 September (from 8 a.m.) – 19 September (until 8 a.m.): Partial closure throughout the day (directions change every 30 min.) and complete nighttime closure from 8 p.m. to 5 a.m.;
• 19 September (from 8 a.m.) – 22 September (until 8 a.m.): Tunnel open;
• 22 September (from 8 a.m.) – 26 September (until 5 a.m.): Partial closure throughout the day (directions change every 30 min.) and complete nighttime closure from 8 p.m. to 5 a.m.;
• 26 September (from 5 a.m.) – 29 September (until 8 a.m.): Partial closure (directions change every 30 min.);
• 29 September (from 8 a.m.) – 1 October (until 5 a.m.): Partial closure throughout the day (directions change every 30 min.) and complete nighttime closure from 8 p.m. to 5 a.m.;
• 1 October (from 5 a.m.) – 19 December (until 8 a.m.): Partial closure throughout the day (directions change every 30 min.) and complete nighttime closure from 11 p.m. to 4.30 a.m.

Source: Dars d.d.